Most US Wind and Solar Projects Win Permits Within About a Year, UMass Amherst Researchers Find

Analysis of 460 projects shows 90% approval rate, though timelines vary widely by state

A new study analyzing hundreds of renewable energy projects across the United States co-led by researchers at the University of Massachusetts Amherst finds that most wind and solar facilities under state jurisdiction receive permits within roughly a year and that 9 in 10 are ultimately approved.

The study, published in the journal Frontiers in Sustainable Energy Policy, examines permitting data for 460 projects across 19 states, analyzing how long it took projects to move from permit application to a final decision and how frequently projects were approved. A companion study also reviewed locally permitted projects in Massachusetts.

Despite the high approval rate overall, researchers found notable variation among states. Kentucky and Mississippi processed applications roughly five months faster than the national average, while Maryland, Ohio, Minnesota and New York took about three months longer. 

Approval rates also varied, ranging from 80% to 100% depending on the state.

Juniper Katz

Governance structures matter. States where permitting boards must incorporate local preferences tend to have higher approval rates—possibly because developers bring projects into compliance before applying.

Juniper Katz, assistant professor of public policy at UMass Amherst


“Governance structures matter,” says Juniper Katz, assistant professor of public policy at UMass Amherst and co-author of the study. “States where permitting boards must incorporate local preferences tend to have higher approval rates—possibly because developers bring projects into compliance before applying.”

Other states have recently shifted authority to centralized state-level siting processes. In Minnesota and New York, centralized oversight coincided with more project proposals but also more complex regulatory dynamics. Ohio stood out for a different reason: After state authority was scaled back, the study documented a 20% cancellation rate among proposed projects.

The findings come as many states revise permitting policies to meet climate and clean energy targets. Although debates often focus on federal permitting reform, the study stresses that most renewable energy facilities in the U.S. are permitted at the state level on private land.

While the national analysis focused on projects reviewed by state authorities, a companion study by the same research team examined permitting timelines in Massachusetts, where most wind and solar projects are reviewed by local governments.

That analysis compiled data on 26 projects in 17 Massachusetts communities and found the permitting process lasted about 250 days on average, with a median of 173 days. Approved projects had shorter timelines, while projects that were canceled or challenged in court saw longer decision times.

Because Massachusetts delegates most land-use authority to municipalities, permitting processes can vary widely among the commonwealth’s 351 cities and towns.

The Massachusetts research provides a reference point as the state finalizes new permitting reforms approved in 2024. The law aims to standardize elements of the permitting process, establish clearer timelines for decisions and strengthen coordination with local governments.

Together, the studies offer one of the most detailed empirical looks to date at how permitting systems shape the pace of renewable energy development in the United States. 

“This dataset provides a baseline—as reforms take effect, researchers and policymakers can now measure whether changes actually shorten timelines or improve outcomes, and which governance structures best balance efficiency with meaningful public participation,” Katz notes.

The research was co-authored by Natalie Baillargeon, a master’s degree candidate at UMass Amherst, together with colleagues from Lawrence Berkeley National Laboratory: Robi Nilson, Lanbing Tao, Will Maddock and Ben Hoen.

Related

Solar arrays in a cranberry bog in Plymouth, Mass.

Public policy researchers Juniper Katz and Natalie Baillargeon examined the trade-offs in the patchwork of approval systems for renewable energy projects.

Wind Energy Turbines

Research by PERI economist Gregor Semieniuk finds that two-thirds of financial losses from fossil fuel assets would affect the top 10% of wealth holders, with half of that affecting the top 1%.

A rural solar farm set amongst forest and field. Credit: Getty Images

Clearing forests to build large-scale solar farms can deliver climate benefits, but those gains often come at a cost to nearby homeowners and ecosystems. Concerns of host communities must be addressed according to researchers.