Site chosen for central heating plant
by Barbara
Pitoniak, News Office staff
|
Long a mainstay of the campus skyline, the
central steam plant could be demolished in 2006 after a planned
new facility goes into operation.
|
new central heating plant for the campus will
be constructed on the west side of campus, adjacent to Route 116
and the Amherst wastewater treatment plant, in the town of Hadley.
Plans call for the existing heating plant on Campus Center Way to
be demolished once the new plant becomes operational, according
to James Cahill, director of Facilities Planning.
"This project is
one of the most significant permitting, design, and construction
efforts undertaken by the University in the last 25 years,"
Cahill said. "We have carefully considered the environmental,
economic, technical, and community concerns affected by the siting
of such an important energy facility. We're pleased to be moving
forward with this project as it is essential to provide reliable
steam to service the existing campus buildings and future campus
development."
The site location was
selected by campus officials and the University of Massachusetts
Building Authority, after an extensive site evaluation process conducted
with the assistance of Vanderweil Engineers Inc., of Boston.
The $80-million central
heating plant project is being funded through the building authority.
Four potential sites
were considered for construction of the new facility: a location
adjacent to the existing central heating plant; the Tillson Farm
heating plant, which included a plan for renovation and expansion;
an area north of Governors Drive across from the PVTA bus garage;
and the location adjacent to the wastewater treatment plant.
According to Cahill,
the Tillson Farm, Campus Center Way, and Governors Drive sites were
eliminated because of cost considerations, traffic and wetland impacts,
and conflicts with the campus master plan.
He said the selected
site near the Amherst wastewater treatment plant offers many positive
attributes for the campus and its neighboring communities. "By
replacing the existing, 60-year-old heating plant and co-locating
it with the wastewater treatment facility, the new heating plant
will significantly conserve natural resources and reduce greenhouse
gas and ozone-producing air emissions, while providing steam and
electric energy to the campus both reliably and economically."
Locating the plant near
campus steam, condensate, and electric distribution systems will
make plant operations more efficient and less costly, Cahill said.
In addition, an existing service road provides convenient access
for fuel deliveries. The location also provides a buffer zone between
the proposed plant, local neighborhoods, and the campus community.
The central heating
plant, to be designed by Vanderweil Engineers Inc., and Cambridge
Seven As-sociates Inc., will burn both fuel oil and natural gas.
(The existing plant primarily burns coal, with oil and natural gas
used to supplement the coal firing.) It will pro-duce steam to heat
campus buildings and to run chillers used for building air conditioning
systems. A gas turbine generator will produce electricity to meet
the base campus electric load of 10 megawatts, or about 10 million
watts per hour.
Two new, 20-inch main
steam lines will run underground in a concrete trench from the heating
plant to connect with the existing campus steam and condensate distribution
piping systems. A new steam connection and condensate return pump
building will be located near the west side of the Campus Center
parking garage.
The new plant is expected
to have significant environmental benefits, said Cahill. "A
substantial reduction in air pollutants will result from the elimination
of coal burning," he says. "Sulfur dioxide emissions will
be cut by nearly a half million pounds per year from existing emission
levels." In addition, Cahill noted, the emission of nitrogen
oxides, which contributes to the production of ozone, could be reduced
by 300,000 pounds, or 150 tons.
Also, during a typical
winter day, Cahill explains, the existing heating plant uses approximately
250,000 gallons of water from the Amherst public water supply system
and its wells. "The University hopes to reuse the effluent
discharge, or gray water, from the Amherst wastewater treatment
facility to make steam in the new plant, and conserve the town's
natural water supply," said Cahill.
The state Department
of Environmental Protection (DEP) and the Executive Office of Environmental
Affairs (EOEA) will monitor environmental permitting requirements
for the new plant. The DEP has approved the air modeling procedures
to be used by the building authority to assess any potential environmental
impacts caused by the new heating plant.
The building authority
will submit an Expanded Environmental Notification Form to EOEA
this summer. The permitting process is expected to take about a
year.
Cahill says the University
hopes to have all environmental permits in hand to break ground
for the plant in the fall of 2003. Construction will take about
two years. The facility is expected to begin start-up operations
by December 2005.
Plans calls for demolishing
the existing heating plant and its chimneys and fuel-handling facilities
in 2006. Much of the debris from the demolition of the building
and the dismantling of equipment will be recycled, Cahill said.
|