Certified LEED v4 BD+C NC Silver
The Student Union building was designed by architect and UMass alumnus Louis Warren Ross in the modernist style and was completed in 1957. Located at the center of the UMass Amherst campus, it was the first campus building dedicated to student organizations and extracurricular activities. The facility contained shared common areas, a large ballroom, and dedicated offices for student organizations and other campus services. At the time of its construction, the Student Union was the largest building on campus and served 4,800 students.
Today, the building supports over 30,000 students and 200 registered student organizations (RSOs). This growth necessitated renovations and infrastructure upgrades to accommodate modern space and service needs of the student body. In the summer of 2016, students and university administrators formed a task force to assess the building’s current conditions and develop a plan for its future. CannonDesign was hired to examine campus spaces for student activities and produce a renovation study for the Student Union.
The $62 million renovation project was jointly funded by the University and a temporary increase in student fees. Designed by Shepley Bulfinch, the renovation revitalized the facility as a modern hub for student activity and interaction, and reconnected the building to its surrounding natural landscape. As a “global campus living room,” the design embraces student entrepreneurship, organizations, and events to support collaboration, multidisciplinary learning, and leadership.
Building Information
Address: 41 Campus Center Way, Amherst, MA 01003-9245
Completed: Fall 2020
Size: 106,867 GSF
Designer / Architect: Shepley Bulfinch
Landscape Architect: CRJA-IBI Group
Structural, Building Envelope, & Sustainability: Thornton Tomasetti
Mechanical, Electrical, & Plumbing: Vanderweil Engineers
Owner's Project Manager: UMass Building Authority
UMass Project Manager: Cleve Carrens, Jeff Quackenbush
UMass Project Planners: Ludmilla Pavlova-Gillham, Andrew Soles
Sustainability
Resources
LEED Project Scorecard
LEED Project Dashboard
Green Building Brochure
Indoor Air Quality
- CO2 sensors ensure adequate fresh air is provided to densely occupied spaces
- Additional designs provide enhanced indoor air quality in the building
- Walk-off grilles in the main entryways prevent cross-contamination
- Over 30% increase in outdoor air ventilation compared to minimum rates
- Heat reflective Thermal comfort survey after occupancy identified opportunities to further improve occupant comfort
Materials + Resources
- Green Housekeeping Program in place to provide clean, green and virus-free environment
- Active green building public education programs
- Use of the building as a teaching tool
- Aiming to divert over 75% of construction wastes from landfill
- Building materials contain recycled content and were extracted, processed, and manufactured regionally
- Wood products were sustainably harvested and certified by Forest Stewardship Council
- Low-emitting materials, such as zero-VOC paints, used during construction ensure a healthy living environment
- Heat reflective
Innovation in Design
- Green Housekeeping Program in place to provide clean, green and virus-free environment
- Active green building public education programs
- Use of the building as a teaching tool
Lighting
- Maximize daylighting
- Most open office spaces are along the windows
- Developed a ceiling profile that allowed use of the full height of the windows
- Glazing to maximize borrowed light and extend views
- High Quality Low Mercury Fixtures
- 75% of all fixtures are LED
- Light sources have a Color Rendering Index (CRI) of 80 or higher
- Rated life of at least 24,000 hours
- Lighting Control
- 90% of individual occupant spaces have individual lighting controls with 3 lighting levels
- Daylight, overhead direct/indirect, task
- All multi-occupant spaces have multi-zone lighting control
- Occupancy Sensors
- Daylight harvesting in key areas:
- Living Room and Main Street
Water Reduction
- Water management was a specific University priority.
- Outdoor water reduction: 30% below baseline
- No outdoor irrigation
- Indoor water reduction: 45% below baseline
- Automatic Flushometers: 1.28 gpf/4.8 lpf
- Automatic Faucets: .5 gpm, 55 second cycle
- Building Level Water Submetering: Mechanical Systems; Student Businesses
- Reuse Water System
Waste Management
- Divert 50% -75% of total construction and demolition materials
- Material Streams
- Cardboard, Glass, Metals, Co-mingled
- University Priority
Optimized Energy Performance
- Zoned air handling with enthalpy
- AHU-1 – General Building Air
- AHU-2– Ballroom Air
- AHU-3 – Kitchens
- Rooftop Air Chiller
- Building Automation System (BAS) with Energy Demand Response integral with UMA’s Metasys load shed program
- Advanced Energy Metering
- All whole-building energy sources and any energy end use that represents 10% min of the total annual building consumption
Materials + Resources
- Enhanced Systems Commissioning (3 pts) – RFS Engineering, MEP Systems CX
- Commission Plan
- Commissioning process activities for MEP systems and assemblies in accordance with ASHRAE Guidelines.
- Post Occupancy Building flush out in mid-December for 21.12 days
- Enhanced and Monitoring-Based Commissioning (4 pts)
- M&V is standard practice at UMA
- Rigorous list of points to be measured and evaluated to assess performance of energy- and water-consuming systems.
- Envelope Commissioning (2 pts) – Building Enclosure Associates, Envelope Cx
- Verify performance of the Union’s thermal envelope.
Photo Gallery
Northeast Exterior Perspective |
Northwest Exterior Perspective |
Event Space |
Bowling Alley |
Lobby |
Concept Diagram |
Ellis Way |
North View |
Images 1-5 courtesy of Special Collections and University Archives, UMass Amherst Libraries. Images 6-8 courtesy of Shepley Bulfinch.
Media
Articles
Shepley Bulfinch Selected for the 108,000-Square-Foot, $55 Million Renovation of UMass Amherst Student Union Building
Boston Real Estate Times - 5/22/2018
Shepley Bulfinch Selected to Revitalize UMass Amherst Student Union Building
PRISM - 5/22/2018
UMass Students Vote To Buy Themselves a $50 Million Student Union Renovation
MassLive - 12/8/2017
UMass Student Referendum To Determine Future Of Student Union
Amherst Wire - 12/1/2017
University of Massachusetts Amherst, UMass Student Union
Shepley Bulfinch - n.d.
Student Union
Special Collections and University Archives, UMass Amherst Libraries - n.d.
UMass Eyes Student Union Building Renovations
Amherst Bulletin - 11/8/2017
Student Union Renovation Begins at UMass Amherst
College Planning & Management - 2/11/2019
Student Union Referendum Passed
UMass Amherst Student Government Association (SGA) - 1/19/2018
Students Approve Funding for Student Union Renovation
University of Massachusetts Amherst News & Media Relations - 12/12/2017