| Heating plant site work set to begin
by Daniel
J. Fitzgibbons, Chronicle staff
eather permitting, site preparation for a planned $85 million central
heating plant is scheduled to begin this week, according to John Mathews,
assistant director for Campus Infrastructure Projects at Facilities
Planning.
After the installation of
a six-foot fence at the site, workers will begin removing the Llewellyn
Derby Track, which hasn't been used for competition for several
years, said Jim Patulak, associate athletic director for Facilities.
The track is located north of the Amherst wastewater treatment plant
on Mullins Way.
Once the track facility is dismantled,
said Mathews, gravel fill will be placed on the site to compress
underlying clay and silt deposits that are remnants of glacial Lake
Hitchcock. Using gravel to pack down the soil was chosen over the
more costly method of driving piles to support the foundation, he
said.
Engineers expect the
site to settle two feet before construction of the heating plant's
foundation begins in 2004, added Mathews. The new plant, which will
provide steam and electricity to the campus, is expected to begin
full operation in 2006. Construction of the facility is being funded
through the University of Massachusetts Building Authority.
The location was selected
by campus and building authority officials after an extensive site
evaluation process conducted with the assistance of Vanderweil Engineers
Inc., of Boston.
When the site was announced
in early July, Facilities Planning director James Cahill said, "We
have carefully considered the environmental, economic, technical,
and community concerns affected by the siting of such an important
energy facility. We're pleased to be moving forward with this project
as it is essential to provide reliable steam to service the existing
campus buildings and future campus development."
The proximity of the
wastewater treatment plant also offers some potential environmental
benefits, said Cahill, who noted that the existing 60-year-old heating
plant uses approximately 250,000 gallons of water from the Amherst
public water supply system and its wells on a typical winter day.
"The University hopes to reuse the effluent discharge, or gray
water, from the Amherst wastewater treatment facility to make steam
in the new plant, and conserve the town's natural water supply,"
says Cahill.
In addition, the new
plant, which will burn both fuel oil and natural gas, is expected
to reduce greenhouse gas and ozone-producing emissions. Coal is
the primary fuel at the current steam plant.
Along with producing
steam to heat campus buildings and running chillers for air conditioning
systems, the new plant's gas turbine generators also will produce
electricity to meet the base campus electric load of 10 megawatts,
or about 10 million watts per hour.
The new plant is being designed
by Vanderweil Engineers Inc., and Cambridge Seven Associates Inc.
According to Mathews,
the architects are taking great care to ensure that the heating
plant will blend with the campus, particularly the nearby Mullins
Center, which also was designed by Cambridge Seven Associates Inc.
A final design is expected next month, he said.
"It's going to
be a nice looking building," said Mathews.
After the new heating
plant goes online, plans call for the demolition of the existing
steam plant, including its chimneys and fuel-handling facilities.
Much of the debris and equipment will be recycled, according to
Cahill.
Campus plans call for
the construction of a new NCAA-quality track and field facility
adjacent to the new soccer and softball fields at the north end
of Stadium Drive. |