Awarded Construction Bids |
Date Posted |
Project Number |
UMA Project Name |
Contact Name |
Awarded to: |
Bid Amount |
|---|---|---|---|---|---|
| 05/01/12 | UMAPP12-172 |
Fleet Services – Remove and Install New Vehicle Lifts | Peter Royer 413.545.0361 | No Bids Received | |
| 05/01/12 | UMAPP12-137 |
Campus – Tree Maintenance and Removal | Peter Royer 413.545.0361 | Northern Tree Service Inc. | NTE $75,000 |
| 03/13/12 | AA12-PR-4431 | Request for Proposal - On Call Construction Vibration Consulting Services | Peter Royer 413.545.0361 | Accentech & Geosonics | $1,350,000 EACH |
| 03/13/12 | UMAPP12-092 |
OIT – Telcom HVAC Systems Maintenance | Peter Royer 413.545.0361 | Rene L. Cote & Sons | $41,347.95 |
| 01/25/12 | UMAPP12-059 |
Campus – Sanitary Sewer, Storm Drain Lines, & Catch Basin Cleaning | Peter Royer 413.545.0361 | C+A Construction Co. Inc. |
$49,999 |
| 03/13/12 | UMAPP12-057 |
Central Heating Plant - Gas Turbine Inlet Cooling Retrofit | Peter Royer 413.545.0361 | NO AWARD | |
| 05/01/12 | UMAPP12-054 |
Request For Proposal - Robsham Visitor’s Center Parking Lot – Develop, design, and install solar photovoltaic array. | Peter Royer 413.545.0361 | No Award Recommended | |
| 03/13/12 | UMAPP12-050 |
Campus – Doors, Windows & Glass Replacement | Peter Royer 413.545.0361 |
Evergreen Construction Corporation | $500,000 |
| 01/25/12 | UMAPP12-049 |
Campus – Hardscape Repair and Excavation Services | Peter Royer 413.545.0361 | C+A Construction Co. Inc. |
$1,000,000 |
| 05/07/12 | UMA12-48 | Brown Seal Air Shafts | Peter Royer 413.545.0361 | No Award | |
| 01/25/12 | UMAPP12-048 | Campus - Chiller Systems Maintenance | Peter Royer 413.545.0361 | Trane U.S. Inc. |
$227,088 |
| 01/25/12 | UMAPP12-043 |
Concrete Recycling |
Peter Royer 413.545.0361 | Associated Building Wreckers | $3,000 |
| 05/01/12 | UMA12-43 | Field Elevator Modernization | Peter Royer 413.545.0361 | No Valid Bids Received | |
| 05/07/12 | UMA12-32 | Lincoln Campus Center Concourse Renovation | Peter Royer 413.545.0361 | Marois Construction | $640,000 |
| 05/01/12 | UMAPP12-031 Addendum #1 - 08/29/11 Addendum #2 - 09/09/11 |
Request for Proposal - Taylor Field - Design and Install Photovoltaic Array | Peter Royer 413.545.0361 | CONEDISON DEVELOPMENT | Revenue Neutral |
| 01/25/12 | UMAPP12-027 |
Campus - Fencing | Peter Royer 413.545.0361 | Hastie Fence Co., Inc | $500,000 |
| 03/13/12 | UMA12-26 | Tobin, Chilled Water Pumps Replacement | Peter Royer 413.545.0361 |
B-G Mechanical Contractors | $82,485 |
| 03/13/12 | UMA12-25 | Southwest Highrise Dryer Exhaust-Kennedy | Peter Royer 413.545.0361 | Five Star Building Corp. | $604,000 |
| 05/01/12 | UMA12-24 | Brooks Barn, Wysocki, Howard Garage Demolition | Peter Royer 413.545.0361 | Jay-Mor Enterprises Inc. | $41,800 |
| 05/07/12 | UMA12-23 | McNamara Reroof & Masonry Repairs | Peter Royer 413.545.0361 | Marois Construction | $1,433,000 |
| 03/13/12 | UMA12-22 | Emerson, James, Melville, and Thoreau Life Safety Upgrades | Peter Royer 413.545.0361 | Aquadro & Cerruti Inc. | $4,944,000 |
| 03/13/12 | UMA12-21 | UMPD, Electronic Key Management System | Peter Royer 413.545.0361 | Deister Electric | $33,820 |
| 03/13/12 | UMA12-20 | Utilities, Northwest Chilled Water Loop, Phase I | Peter Royer 413.545.0361 |
Five Star Building Corp. | $1,937,799 |
| 05/01/12 | UMA12-19 | Grayson & Field Window Replacement | Peter Royer 413.545.0361 |
GVW Inc. | $7,619,129 |
| 03/13/12 | UMA12-18 | Housing, Finish Upgrade 2012-Lewis & Thatcher | Peter Royer 413.545.0361 | Western Builders Inc | $2,867,350 |
| 03/13/12 | UMA12-17 | Bartlett - New Electrical Service | Peter Royer 413.545.0361 | Collins Electric Co. | $196,856 |
| 03/13/12 | UMA12-16 | ISOM Card Access | Peter Royer 413.545.0361 | C G L Electrontic Security Inc. | $11,671.03 |
| 03/13/12 | UMA12-15 | Mullins Center Cooling Tower Repairs | Peter Royer 413.545.0361 | B-G Mechanical Contractors | $106,944 |
| 01/25/12 | UMA12-14 | Lincoln Campus Center Service Elevator Modernization | Peter Royer 413.545.0361 | Bay State Elevator |
$397,786 |
| 01/25/12 | UMA12-13 RE-BID | Street Sweeper for Southwest Concourse - Phase II | Peter Royer 413.545.0361 | National Water Main Cleaning Co |
$14,850 |
| 01/25/12 | UMA12-11 | Worcester Dining Commons - Roof Fence | Peter Royer 413.545.0361 | Hastie Fence Co., Inc. |
$12,595 |
| 03/13/12 | UMA12-10 | Hasbrouck Roof Replacement | Peter Royer 413.545.0361 | J. D. Rivet & Co., Inc. | $674,000 |
| 03/13/12 | UMA12-09 | Structural Testing Facility | Peter Royer 413.545.0361 |
NO AWARD | |
| 01/25/12 | UMA12-08 | Bowditch Lodge, Entances | Peter Royer 413.545.0361 | Warner Bros. LLC |
$72,210 |
| 01/25/12 | UMA12-07 |
Dubois Cafe |
Peter Royer 413.545.0361 | Eastern General Contractors Inc. |
$459,000 |
| 01/25/12 | UMA12-04 |
Lincoln Campus Center Pedestrian Tunnel Renovations | Peter Royer 413.545.0361 | Evergreen Construction Corporation |
$222,780 |
| 05/01/12 | AA11-PR-4129 Addendum #1 - 03/16/11 |
Request for Qualifications to provide Environmental Science and Management Consultant | Peter Royer 413.545.0361 | 7 Firms Selected | $1,350,000 each |
| 05/07/12 | AA11-PR-4115 | Request for Qualifications to Provide Cost Consulting Services | Peter Royer 413.545.0361 |
|
$1,000,000 each |
|
|||
|