Network Infrastructure Project

Project Goals 

The primary goal of the Network Infrastructure Project is to provide better, faster network connectivity and fulfill the academic, social connectivity, and general communication needs of our students, faculty, and staff, as these needs continue to evolve. The multi-year project includes work on both the core network and infrastructure at the building level. Work has started on the core network foundation. Some building work will need to wait for core upgrades; other building work can be completed in parallel. 

Recent Progress

Core foundation network investments: over $18 million invested since summer 2014. 

MAJOR SHARED FOUNDATIONAL INFRASTRUCTURE UPGRADES

Location Work Completed  Percentage of Work Complete
Project Started: Fall 2015
Major Network Sites Major Network Conversion & Equipment Upgrades
  45% Complete
Project Started: Summer 2015
Data Center Network Major Network Conversion & Equipment Upgrades
75% Complete  
Project Started: Spring 2015
Major Network Sites Backup Electrical Power Improvements
100% Complete


BUILDING UPGRADES

Location Work Completed Percentage of Work Complete
Project Started: Spring 2016
Arnold House All Wireless Access Points Updated & Network Fully Upgraded
100% Complete
Baker All Wireless Access Points Updated & Network Fully Upgraded
100% Complete
Bartlett All Wireless Access Points Updated & Network Fully Upgraded
100% Complete
Brett All Wireless Access Points Updated & Network Fully Upgraded
100% Complete
Brooks  All Wireless Access Points Updated & Network Fully Upgraded
100% Complete
Brown  All Wireless Access Points Updated & Network Fully Upgraded
100% Complete
Butterfield  All Wireless Access Points Updated & Network Fully Upgraded
100% Complete
Cance  All Wireless Access Points Updated & Network Fully Upgraded
100% Complete
Cashin  All Wireless Access Points Updated & Network Fully Upgraded
100% Complete
Chadbourne All Wireless Access Points Updated & Network Fully Upgraded
100% Complete
Coolidge Building  All Wireless Access Points Updated & Network Fully Upgraded
100% Complete
Crabtree  All Wireless Access Points Updated & Network Fully Upgraded
100% Complete
Crampton  All Wireless Access Points Updated & Network Fully Upgraded
100% Complete
Champions Center All Wireless Access Points Updated & Network Fully Upgraded
100% Complete
Du Bois Library All Wireless Access Points Updated & Network Fully Upgraded
100% Complete
Dwight All Wireless Access Points Updated & Network Fully Upgraded
100% Complete
Emerson  All Wireless Access Points Updated & Network Fully Upgraded
100% Complete
Emily Dickinson  All Wireless Access Points Updated & Network Fully Upgraded
100% Complete
Field  All Wireless Access Points Updated & Network Fully Upgraded
100% Complete
Field House 1   Phase 1: Network Prep for Faster Connections
100% Complete
Fine Arts Center All Wireless Access Points Updated & Network Fully Upgraded
100% Complete
Flint Labs All Wireless Access Points Updated & Network Fully Upgraded
100% Complete
Gorman  All Wireless Access Points Updated & Network Fully Upgraded
100% Complete
Goodell All Wireless Access Points Updated & Network Fully Upgraded
100% Complete
Gordon Hall All Wireless Access Points Updated & Network Fully Upgraded
100% Complete
Grayson  All Wireless Access Points Updated & Network Fully Upgraded
100% Complete
Greenough All Wireless Access Points Updated & Network Fully Upgraded
100% Complete
Hamlin All Wireless Access Points Updated & Network Fully Upgraded
100% Complete
Hampshire DC  All Wireless Access Points Updated & Network Fully Upgraded
100% Complete
Herter All Wireless Access Points Updated & Network Fully Upgraded
100% Complete
Integrated Science Building All Wireless Access Points Updated & Network Fully Upgraded
100% Complete
Johnson All Wireless Access Points Updated & Network Fully Upgraded
100% Complete
Knowlton All Wireless Access Points Updated & Network Fully Upgraded
100% Complete
Leach  All Wireless Access Points Updated & Network Fully Upgraded
100% Complete
Lederle Graduate Research Tower All Wireless Access Points Updated & Network Fully Upgraded
100% Complete
Lewis All Wireless Access Points Updated & Network Fully Upgraded
100% Complete
Machmer All Wireless Access Points Updated & Network Fully Upgraded
100% Complete
Mary Lyon  All Wireless Access Points Updated & Network Fully Upgraded
100% Complete
McNamara  All Wireless Access Points Updated & Network Fully Upgraded
100% Complete
Memorial Hall All Wireless Access Points Updated & Network Fully Upgraded
100% Complete
Montague House All Wireless Access Points Updated & Network Fully Upgraded
100% Complete
Morrill Science I, II, III, IV All Wireless Access Points Updated & Network Fully Upgraded
100% Complete
Parking Garage All Wireless Access Points Updated & Network Fully Upgraded
100% Complete
PVTA Bus Garage All Wireless Access Points Updated & Network Fully Upgraded
100% Complete
Stockbridge Hall All Wireless Access Points Updated & Network Fully Upgraded
100% Complete
Thatcher All Wireless Access Points Updated & Network Fully Upgraded
100% Complete
Thompson All Wireless Access Points Updated & Network Fully Upgraded
100% Complete
University Health Services All Wireless Access Points Updated & Network Fully Upgraded
100% Complete
UMass Police Department All Wireless Access Points Updated & Network Fully Upgraded
100% Complete
Webster 

All Wireless Access Points Updated & Network Fully Upgraded

100% Complete
Wheeler 

All Wireless Access Points Updated & Network Fully Upgraded

100% Complete
Whitmore All Wireless Access Points Updated & Network Fully Upgraded
100% Complete
Project Started: Fall 2015
Lederle Graduate Research Center All Wireless Access Points Replaced
100% Complete
Life Sciences Laboratories All Wireless Access Points Updated & Network Fully Upgraded
100% Complete
North Village Phase 1: Network Prep for Faster Connections
100% Complete
North Village    Phase 2: Purchase & Installation
  15% Complete
North Village Phase 3: Wireless Installation
  5% Complete
George M. Parks Marching Band Building Phase 1: Network Prep for Faster Connections
100% Complete
Project Started: Summer 2015
Campus Center Wireless Upgrades on the 1st, 8th & 9th Floor
100% Complete
Campus Classrooms Wireless Access Point Upgrades
  40% Complete
Champions Center    All Wireless Access Points Updated & Network Fully Upgraded
100% Complete
Furcolo  All Wireless Access Points Updated & Network Fully Upgraded
100% Complete
Isenberg School of Management All Wireless Access Points Replaced
100% Complete
Flint Labs All Wireless Access Points Updated & Network Fully Upgraded
100% Complete
Student Union Phase 1: Network Prep for Faster Connections
100% Complete
Studio Arts Building All Access Points Updated & Network Fully Upgraded
100% Complete

Network Maintenance

Location Work Completed Percentage of Work Complete
Project Started: Spring 2016
Residential Halls Residential Hall Maintenance
95% Complete
Project Started: Fall 2015
Residential Halls Residential Hall Maintenance
100% Complete
Project Started: Summer 2015
Residential Halls Summer Residential Hall Maintenance
100% Complete

 

Last Updated: February 23, 2017

 

Other network updates

9/28/15 Update on campus network performance

More Information:

Shared Infrastructure Technology Fee & Network Modernization FAQ