Construction News for
| |
|
Construction Underway The walkway across the north end of the Campus Pond will remain closed throughout construction. Walking east-west will require traveling around the Pond at the south end (Fine Arts Center), or traveling through or around Hasbrouck Lab and the Campus Center to the north. In some cases, this may add extra travel time, but we're hoping to minimize that by laying out clear and reliable alternate routes to and from various points on campus. See map, top left. The contractor's two-week construction look-ahead is available here.Questions about this project should be directed to the project manager, Jeff Quackenbush at 5-6453 or jquacken@facil.umass.edu. For more information about this project, see the Academic Classroom Building Project information page. | |
|
Commonwealth Honors College Residential Complex
|
A four-week construction activity look-ahead, covering May 1 through May 29, is available here. Note that work periods are expected to include Saturdays and Sundays for specific activities. Summer Utility Work and Detours Refer to maps, left; click for larger images. May 7-June 1
June 1 - June 18
July 9 - July 20
July 21 - August 19
Speed Limit Reduced on Commonwealth Ave. Due to heavy construction activity and traffic associated with the Commonwealth Honors College Residential Project, the speed limit on Commonwealth Avenue between Massachusetts Avenue and Campus Center Way has been reduced to 20MPH. This speed limit is being strictly enforced by the UMass Police. As a designated "work zone," fines for speeding in the area will be doubled. The reduced speed limit will be in effect until further notice. Questions concerning campus traffic law enforcement should be directed to the UMass Police Department at 545-2121. Questions about this project should be directed to the Facilities Planning project manager, Andy Soles, at 5-6464 or asoles@admin.umass.edu. A YouTube video about the project, produced by the UMass Amherst Office of News & Media Relations, can be found here. |
|
| |
|
Du Bois Library |
The Du Bois Library elevators are currently being replaced with new machinery, state of the art controls, new cars and new enhanced lobby entrances. Current Status: Elevator Cars #1, 2 and 5 have been replaced and are in public use. Car #4 is currently under construction and is anticipated to be complete by the middle of May, 2012. Car #3 is still old equipment and only accesses lower floors up to Floor 16. Future Schedule: Once Car #4 will return to service in May; Car #3 will be removed and replaced over the summer months. Car #2 will also be taken out of public service to assist with construction activities over the summer months. |
|
| |
|
Goessmann Laboratory Renovation ![]() |
Construction site fencing has been erected for extensive utility and mechanical work (see map, left). Special Advisories:
On Friday, May 18th, a portion of Red Lot 65 north of Draper will be blocked off for construction
delivery. The spaces will reopen after the delivery is made. Alternate parking is available in other sections of Red
Lot 65 or Red Lot 45. The contractor has blocked off the walkway between New Goessmann and Lederle Tower A. The walkway will not be accessible for several months, and pedestrians will be directed around the work site. The project is expected to be completed in January of 2013 and includes the following renovations, installations, and new construction: • New mechanical addition (west end of Goessmann Addition - see rendering, below left) |
|
| |
|
NIH Renovations. Using grants provided by the National Institutes of Health (NIH) under the American Recovery and Reinvestment Act, renovations to laboratories in Towers A and C have begun. Contractor equipment staging fences have gone up in the area (see graphic, left). Work is expected to be completed in October of next year. Following is the current two-week construction activity look-ahead:
MEP Upgrades. We'll be making mechanical, electrical and plumbing (MEP) upgrades throughout the GRC complex that began in August and finishing in March of 2012. These projects may require restricted access to some areas and/or scheduled utility interruptions. | |
|
| |
|
Sidewalk Construction Restricts ISB Entrances Site work and sidewalk construction at and around the LSL is restricting doorways at the Integrated Science Building (ISB) now through mid-June. See site plan, top left. The ISB south entrance (located on the east side of the southern wing of the building) will be closed through June 3. Temporary sidewalks will be in place from Skinner Hall and the ISB to North Pleasant Street during construction. The entrance at the northeast end of the building will be closed from June 4 until June 18. Exits to the north/west will be unaffected. A Portion of Lot 63 Temporarily Closed Beginning May 14 Access to the Integrated Science Building and the Worcester DC loading docks will remain open during construction. Lot 63 permit holders are asked to park in the remaining portion of Lot 63, or in Lots 43, 27, 44 or the Upper Parking Garage. Please contact Parking Services at 413-545-0065 if you have any questions regarding parking. Thatcher Road CLOSED to through traffic for ten weeks beginning Monday, April 23 Thatcher road will be closed from Chancellor's Way to Worcester DC in order to build concrete retaining walls for the LSL. The closure will be from 9:00 AM to 3:00 PM week days, starting on April 23, 2012 and extending for approximately 10 weeks (end July 1, 2012). The pedestrian trail from Orchard Hill to Worcester DC will remain open as will the entrance to the University Health Services parking lot. The road will not be closed during Commencement, May 11 and 12. Electronic signs warning of the road closure will be installed on Thatcher Road at the intersections of Eastman Lane and Chancellor's Way. Police officers will also be provided. Pedestrian traffic along the entire length of Thatcher Road will be maintained (see map, left). Site Fence The site fence runs from the Durfee Conservatory Lot in a northerly direction along the west side of Thatcher Road; then westerly to the east end of the Life Sciences Building; then southerly along the east side of Stockbridge Road; and then easterly to the Durfee Lot. As indicated by the locus map (bottom left), an accessible pedestrian route has been established east of the site along Thatcher Road, south of the site through the Durfee lot, and west of the site along Stockbridge Road. LED traffic signs are positioned along Thatcher Road. The site fence will be in place for the duration of the project through May of 2012. Please direct questions or comments concerning the LSL project to the UMass Facilities Planning Project Manager, Jeff Quackenbush at 5-6453, or jquacken@facil.umass.edu. A real-time web cam of the construction site is available on the project information page. | |
| |
|
|
Renovation of the Lincoln Campus Center Concourse is scheduled to begin on Monday, May 21. The project will include a new ceiling, new lighting, acoustical treatments, a new service desk area, and upgrades to the mechanical, electrical and plumbing systems. Regular work hours will be from 7 a.m. to 6 p.m., Monday through Friday; however, some weekend and nighttime work may occur. Significant construction noise and vibration will be associated with the project, particularly during the first two weeks of work as the contractor performs demolition and concrete cutting. Those wishing to use Lincoln Campus Center facilities, especially in proximity to the Concourse, are urged to contact Conference Services at 7-8100 to discuss space options. The Concourse will remain open and accessible during construction, though pathways will be restricted. The UMass Bookstore will remain open, and food service will continue to be available. This renovation is expected to be complete by the end of the summer. Questions concerning the Lincoln Campus Center Concourse renovation should be directed to the UMass Facilities Planning project manager, Ivan Chow, at 5-2644 or ischow@facil.umass.edu. | |
|
| |
|
|
Work has begun on new, underground pipe lines that will eventually provide chilled water to the northwest quadrant of campus. The schedule of phased work has changed to accommodate building use requirements and the final exam schedule. See map, left, for the current work schedule. Some sidewalks around the engineering quad and between the quad and Goessmann will be closed throughout construction. Walking north-south will require traveling around construction fencing and egress roads for construction traffic. Alternate pedestrian routes and detours will be posted. Questions about the project should be directed to the FP project manager, Ted Davis, at 545-6515; tdavis@facil.umass.edu. [Top of the page] |
|
| |
| Southwest Concourse Reconstruction |
The project is essentially complete, with landscaping adjustments and reclamation of the southwest lawn area to continue, weather permitting. Questions about the project should be directed to the FP project manager, Bruce Thomas, at 577-1717; bthomas@admin.umass.edu. [Top of the page] |
|
| |
|
Questions and comments should be directed to Jim Hunt, Communications Manager; jhunt@facil.umass.edu; (413) 577-4767. | |

















