|
|
|
|
Student Activities Student Projects
Internships: Residential Design, from Conception to Completion.
Student: John LaBreck
Faculty Sponsor: Peggi Clouston
Project Type: Independent Study
Year: 2005
Introduction:
During my 2005 winter session brake from college I looked
to further my education in a somewhat different way. I was
looking for hands-on experience in the field of Residential
Construction rather than more coursework. I felt strongly
that some on-site experience in the field would be a great
asset for my resume and for my upcoming career. I have
owned a residential design business for the past three years
and wanted some more experience within the other areas of
the field. Developing the construction drawings was a start
but I wanted to tie it all together. Some of the areas I
wished to work more closely within included: framing,
estimating, on-site and off-site leadership, etc. I was given
the opportunity to work for a residential builder that I had
just recently done a set of construction drawings for and
the project he happened to be starting during the month of
January was the project that I had just finished for him.
This project was not your typical ranch or colonial box. It
was a 5-unit set of luxury townhouses that totalled over
10,000 square feet of living space. I quickly set up an
internship with the builder realizing that this would be a
great opportunity.
Aim of Internship :
The aim of this internship was to take those plans I had just
finished, which was an accomplishment in itself, and
actually get on-site and put it together. The construction
project will be reviewed from start to finish outlining any
coursework that was involved within the project. Before I
had left at the end of January, the townhouses had been
framed, roofed, and the windows were installed. I actually
got to see and install the LVL's, I-Joists, and steel beams I
had sized back during the design phase. I was reading these
plans and I was developing change orders in the office from
the plans that I had designed. The amount of experience I
took from this job was amazing and I don't think I could
have asked for a better learning experience.
Design Process :
My part of the project was to develop a working set of
construction drawings designed around site conditions,
zoning ordinances, building codes, and the developer’s
needs and wants.

Framing Process :
The framing started the first day I was on-site. It couldn’t
have worked out any better. The foundation had already been
poured and was ready for the sill to be installed. Shown are pictures of completed foundation, and complete construction.

Related Coursework :
Throughout the entire project much of the work that was
encountered involved BMATWT coursework in a variety of
ways. Designing the plans with AutoCAD and writing up
change orders during the building process are just a couple
of the things that involved knowledge taken from the
classroom. Below, I will go into more depth on a couple
areas of the project that involved large amounts of
experience and knowledge taken from the classroom.

In order to design these various beams a couple
different beam report programs were used. Many
times these beam reports are required by building
inspectors. These reports verify that the beam can
withstand the numerous loads acting upon it.
Loading can include: uniformly distributed loads,
span carried loads, and point loads. Even though
these programs allow calculations to be done much
faster than those done by hand, they don’t excuse
the knowledge needed to derive proper live load,
dead load, and deflection ratings. Being able to be
on-site installing these various beams was a great
learning experience. Actually seeing the post that
that supports the beam and the loads acting on
beam was a great visual learning experience.
Seeing these things first hand will make my next
set of plans be that much easier. I can take this
experience back to the drawing board.
On a few occasions change orders needed to be
developed. Most of the time these change orders
were brought on by the buyers of the townhouses.
I was often sent back to the company office to deal
with these changes. On top of coming up with new
prices and material lists based on the changes the
overall job schedule needed to be amended every
time this happened to account for lost time Below I
have listed a few of the building components that
were changed after the plans were finished and
after construction had already begun.
- Due to unforseen grade conditions at the start of
the project foundation walls needed to be
amended.
- Many cathedral ceilings within the units were
abandoned in order to achieve extra bedrooms
and additional square footage.
- Interior walls were added, moved, removed
- Instead of decks on the back of many of the units the new homeowner’s preferred 3-season rooms.
Conclusion :
In the end, this project brought together both the
knowledge taken from the classroom along with my
prior experience within the field. I realized how
much coursework from Building Materials and
Wood Technology tied together with a full fledged
construction project. I also realized how much more
you can learn from a project that you are building
both on a piece of paper and in real life. I took away
many new skills and enhanced many that I already
had.
|
Contact Information:
Dave Damery, Director
Building Materials and Wood Technology
120 Holdsworth Natural Resources Center
University of Massachusetts, Amherst, MA 01003
Tel: +1 (413) 545-1770
|
|
|
|